Activity ID
665
Approval Date
Country
ESMAP Reviewer
Not assigned
Fiscal Year
Mitigation Measures
A high-level multi-agency steering committee was created to assist and liaise with the Bank team and the consultant. Also, the fact that this exercise was demand-driven by the client should mitigate the risk of this activity not reaching a meaningful and useful conclusion.
Old nid
67739
Outcome Details
Outcome 1: (Actual) Policy/Strategy Informed.
As recommended by ESMAP's Energy Sector Master Plan activity, the government improved electricity billing and metering systems and has started to charge industrial customers for reactive power since July 2009.
As recommended by ESMAP's Energy Sector Master Plan activity, the government improved electricity billing and metering systems and has started to charge industrial customers for reactive power since July 2009.
Outputs
No outputs defined!
Product Line
Economic and Sector Work (ESW)
Programs
Project ID
P107067
Region
Responsible Unit
MNSSD
Risk Description
The primary risk is the lack of willingness on the Government and sector stakeholder's part to contribute and participate actively and transparently in a process that requires close coordination, information sharing, and collective trust. This is not an exercise the Djiboutians are used to.
SAP Commitments
0
SAP Disbursements
0
SAP Implementation Rate
0
SAP Total Disbursement
134,841
Status
Closed
Summary
The activity helps to finance a specialized consulting firm to assist the Bank in the following key components of the Energy Sector Master Plan: 1. Data Collection and Planning Criteria 2. Load Forecast 3. Supply-Side Options (Electricity Generation) 4. Review of Supply-side Options 5. Transmission & Distribution options 6. Optimal Investment Plan & associated requirements 7. Training
Team Leader
Pierre Audinet